Darling Down’s Power Station

Browse through just some of the Pipe & Civil Projects our team have completed.

Darling Down’s Power Station Water Pipeline Project. (CH 2M Hill)

Project Overview

Category: Pipe & Civil Projects

Type Of Contract: Construct Only

Location: Dalby Queensland

Construction Period: 3 Months

Contract Value: $1,200,000.00

Client: Origin Darling Downs Power Station

Project Description

Darling Down’s Power Station project involved excavation, pipe laying and backfilling of 5.5km 160mm PE pipe from the Darling Downs Power Station to an artesian bore to supply water for the cooling towers in the power station.

Christopher Contracting used our 755 Vermeer trencher, Flow-con truck and other earth moving equipment to construct this project with an average of 400m a day of pipe laid and backfilled.

The design required C/C to directional drill under APA major gas lines and excavate under Arrows CSG lines which was completed without incident. CC Pipe and Civil received a letter of recommendation from Main Roads, APA Gas and the Darling Downs council for our works around and along their roads and easements. Restoration of the alignment involved road repair and seeding.

 

Project Gallery

Please click on the photographs to view larger:

Darling Down’s Power Station Water Pipeline Project. (CH 2M Hill)
Darling Down’s Power Station Water Pipeline Project. (CH 2M Hill)

Committed to providing a safe and healthy work environment